Can kitchen demolition start before the building permit is issued in Ottawa?
Can kitchen demolition start before the building permit is issued in Ottawa?
The Building Code Act is direct on this point: "No person shall construct or demolish a building or cause a building to be constructed or demolished unless a permit has been issued." Where a job needs a permit, the permit comes first, and the Act names demolition as well as construction.
That said, not every kitchen task triggers a permit. The City of Ottawa lists certain work as exempt, including replacing cabinets where plumbing fixtures stay in place, new flooring, painting and decorating, and replacing doors or windows in the same opening. If every part of your kitchen job sits on that exempt list, nothing on the City's permit list is involved. But if the scope includes anything on the permit side, such as adding or removing walls to create different room sizes or uses, or alterations to a plumbing system beyond replacing existing fixtures, the permit must be in hand before that work begins. The City's FAQ puts it plainly: "It is the owner's responsibility to ensure that a Building Permit is obtained when required," and both the owner and the contractor are equally liable under the Building Code Act.
One practical point on sequencing: Health Canada says that in an older home, a professional should test for asbestos before any demolition begins, and if asbestos is found, to hire a qualified asbestos removal specialist to remove it safely. If the home was built before 1960, Health Canada also notes it probably contains lead-based paint, and sanding or heat guns should not be used to remove it. Asbestos testing and removal questions belong to ottawaabatement.com.
For any part of the job that is not clearly on the City's exempt list, including work whose permit status is uncertain, the City's Building Code Services is the right place to ask before anything comes down. The City's submission requirements for renovation permits include floor plans showing plumbing fixture locations.
A few things worth confirming in writing before the job starts:
- which parts of the scope the contractor considers permit-required and which exempt
- who applies for the building permit and who is named on it
- whether asbestos or lead testing is part of the pre-demolition plan
Want this done at your place?
Tell us what you want to change in your kitchen and we'll send it to local Ottawa kitchen renovation contractors, who reply by email. We send it out to local contractors for you. Free, no pressure.
Kitchen Reno IQ -- Built from the Ontario Building Code, Ontario regulations and City of Ottawa sources and real construction experience. Answers are for informational purposes only and are not a professional assessment.
Ready to Get Quotes?
Find local kitchen renovation contractors in Ottawa. Free matching, no obligation.